Sr. No. | Description of Project | Remarks |
1 | Provision of Flowline / on plot hook up, design and construction services – MEDCO LLC (Karim Small Field)
MEDCO Energy LLC awarded 5 years’ service contract on August 2016 for procurement and construction of Flowline, Header, and water injection line and on plot piping hook ups cover CS+HDPE materials. |
In Progress |
2 | Procurement, Fabrication And Supply Of Multiport Selector Valve (MSV) Skids - 4 Years
Engineering, design, procurement, manufacturing, fabrication, assembly, inspection, testing, certification, painting, packing, logistics, and transportation of Multiport Selector Valve Skids (MSV Skids) for a period of four (4) years to DALEEL site. |
In Progress |
3 | Procurement and Construction of Flowlines – Petrogas Rima (Rima Small Field)
Petrogas Rima awarded 3 + 2 years’ service contract on Nov 2019 for Engineering, Procurement and construction of flowline, hearder, pipeline, station piping, equipment erection and hook up piping coves CS+HDPE materials |
In Progress |
4 | Provision of On-plot and Off-plot Mechanical Construction Services – CC Energy Development SAL (Block 3 &4))
CC Energy Development SAL awarded 5 years’ service contract on Feb 2020 to perform on-plot and off-plot mechanical construction works in brown and green fields related to Company projects at Block 3 & 4 on call-offs basis. |
In Progress |
5 | ARA E&P 142 EPC Project for Fiscal Metering Station Engineering, Procurement, Construction and Commissioning of Fiscal Metering Station at Qarat Al Milh location near PDO-MOL Tie in location, the contract Awarded by ARA Petroleum E&P LLC.
|
In Progress |
6 | ARA E&P 144 Flowline, OHL Hookup - Service Contract Procurement and Installation of Flowline, OHL Construction and well hookup for three years of Service contract at Qarat Al milh Location, the contract Awarded by ARA Petroleum E&P LLC. |
In Progress |
7 | ARA E&P 118 Preventive and Corrective Maintenance Contracts Maintenance Contract for Preventive and Corrective Maintence works service contract for three years at Qarat Al Milh, the contract Awarded by ARA Petroleum E&P LLC. |
In Progress |
8 | PA 00700 EPC for Permanent Production Separators - 4 Nos Detailed Engineering, Procurement and Construction of Permanent Production Separators for 4 different location and related Civil, Mechanical, Electrical and Instrumentation actvities for the same, this contract Awarded by CC Energy Development SAL. |
In Progress |